J-26-0181

Ulan West Operations — LW W6 face — onsite roof support overhaul, shields 1–74
Demo 06 Oct 2026
← Jobs Quote Q-26-0411
$507,241value (ex GST)
$330,635cost to date · 100% done
$330,635forecast cost · budget $321,005
34.8%forecast margin · quoted 36.7%
$0invoiced
Workshop items+ Book in
No workshop items on this job.
Invoices
Not invoiced yet.
Coststimesheets, parts issued, subcontract & freight
DateCategoryDescriptionRefAmount
27 Aug 2026 Labour Timesheets — week ending 27 Aug TS-4230 $73,819.00
22 Aug 2026 Labour Timesheets — week ending 22 Aug TS-4852 $84,336.00
19 Aug 2026 Freight Freight — Mudgee ↔ site AP-20504 $3,811.00
19 Aug 2026 Parts & materials Parts issued from Mudgee stores AP-20912 $27,811.00
16 Aug 2026 Labour Timesheets — week ending 16 Aug TS-4778 $80,874.00
11 Aug 2026 Labour Timesheets — week ending 11 Aug TS-4170 $59,984.00
Onsite overhaulComplete
Customer
Ulan West Operations
Location
Ulan West — LW W6 face
Dates
05 Aug 2026 – 02 Sep 2026
Supervisor
Mick Sullivan
Crew
10
Order no.
4500609922
Cost by category
Labour$299,013
Parts & materials$27,811
Freight$3,811