Step 8 of 10 — Jobs. Follow each job from Planned to Complete. Drag it to Invoiced to raise the tax invoice. Next: Workshop →
32 cards · $6,361,903 · drag between columns
Planned 5 · $432,300
J-26-0191 Offsite
Advance ram overhaul — 18 × 140 mm
Appin Mine · 12 Oct – 5 Nov $40,200
0% · Brad Kelly
J-26-0205 Offsite
Shuttle car gearboxes — 2 × rebuild
Wambo Underground · 14 Oct – 3 Nov $34,000
0% · Brad Kelly
J-26-0199 Offsite
Shearer ranging arm overhaul — tailgate
Broadmeadow Mine · 18 Oct – 27 Nov $93,800
0% · Brad Kelly
J-26-0184 Onsite
LW 211 maingate drive & BSL onsite overhaul
Moranbah North Mine · 24 Oct – 4 Nov $186,080
0% · Nathan Pye
J-26-0198 Onsite
Monorail overhaul — 140 trolleys
Kestrel Mine · 30 Oct – 9 Nov $78,220
0% · Nathan Pye
Drop here
In progress 14 · $2,593,826
J-26-0206 CM
Condition monitoring program FY27 — Ulan West Operations
Ulan West Operations · 1 Jul – 1 Jul $257,600
27% · Sophie Lindqvist
J-26-0207 CM
Condition monitoring program FY27 — Moolarben Underground
Moolarben Underground · 1 Jul – 1 Jul $238,090
27% · Sophie Lindqvist
J-26-0208 CM
Condition monitoring program FY27 — Narrabri Underground
Narrabri Underground · 1 Jul – 1 Jul $95,600
27% · Sophie Lindqvist
J-26-0209 CM
Condition monitoring program FY27 — Springvale Mine
Springvale Mine · 1 Jul – 1 Jul $95,600
27% · Sophie Lindqvist
J-26-0210 CM
Condition monitoring program FY27 — Mandalong Mine
Mandalong Mine · 1 Jul – 1 Jul $93,910
27% · Sophie Lindqvist
J-26-0211 CM
Condition monitoring program FY27 — Wambo Underground
Wambo Underground · 1 Jul – 1 Jul $92,220
27% · Sophie Lindqvist
J-26-0212 CM
Condition monitoring program FY27 — Moranbah North Mine
Moranbah North Mine · 1 Jul – 1 Jul $95,600
27% · Sophie Lindqvist
J-26-0196 Engineering
Canopy tip extension — design & certification
Airly Mine · 6 Sep – 26 Oct $47,100
60% · Tom Walsh
J-26-0185 Offsite
Exchange leg overhaul — 24 × 400 mm legs (W6 rotation pool)
Ulan West Operations · 15 Sep – 20 Oct $154,800
50% · Brad Kelly
J-26-0194 Offsite
Emulsion pump overhaul — 2 × BRW630/37.5
Narrabri Underground · 20 Sep – 14 Oct $61,400
60% · Brad Kelly
J-26-0186 Offsite
DA ram reseal — 40 × 160 mm rams
Moolarben Underground · 22 Sep – 16 Oct $68,400
55% · Brad Kelly · over budget
J-26-0188 Offsite
Feeder breaker FB-01 — pick drum rebuild
Wambo Underground · 24 Sep – 15 Oct $26,300
40% · Brad Kelly
J-26-0190 Offsite
Shield control valve banks — 30 × service & bench test
Metropolitan Mine · 26 Sep – 17 Oct $45,000
35% · Brad Kelly
J-26-0183 LW relocation
LW 110 → LW 111 longwall relocation — take-off & install
Narrabri Underground · 27 Sep – 18 Oct $1,222,206
45% · Dean Purcell · over budget
Drop here
QA & handover 3 · $440,153
J-26-0195 Offsite
Leg cylinder overhaul — 12 × 320 mm
Grosvenor Mine · 1 Sep – 5 Oct $68,160
92% · Brad Kelly
J-26-0187 Offsite
Shuttle car SC-02 — traction gearbox rebuild
Springvale Mine · 10 Sep – 4 Oct $34,000
95% · Brad Kelly
J-26-0200 Onsite
LW 107 mid-panel shield service — 136 shields
Moolarben Underground · 18 Sep – 3 Oct $337,993
97% · Mick Sullivan · over budget
Drop here
Complete 4 · $583,821
J-26-0181 Onsite
LW W6 face — onsite roof support overhaul, shields 1–74
Ulan West Operations · 5 Aug – 2 Sep $507,241
100% · Mick Sullivan
J-26-0197 Engineering
Shield base-lift cylinder modification — design review
Ulan West Operations · 12 Aug – 16 Sep $12,480
100% · Tom Walsh
J-26-0203 Offsite
Continuous miner CM-01 — cutter gearbox overhaul
Springvale Mine · 22 Aug – 24 Sep $36,900
100% · Brad Kelly
J-26-0189 Offsite
BSL sprocket assembly rebuild — spare
Mandalong Mine · 27 Aug – 28 Sep $27,200
100% · Brad Kelly
Drop here
Invoiced 6 · $2,311,803
J-26-0202 LW relocation
LW 24 → LW 25 longwall relocation
Mandalong Mine · 9 May – 3 Jun $1,106,120
100% · Dean Purcell
J-26-0182 LW relocation
LW 106 → LW 107 longwall relocation
Moolarben Underground · 31 May – 24 Jun $983,028
100% · Mick Sullivan
J-26-0204 Onsite
Pump station — onsite plunger & valve change
Metropolitan Mine · 18 Jun – 24 Jun $28,494
100% · Josh Tranter
J-26-0193 Offsite
AFC tailgate gearbox overhaul
Moranbah North Mine · 2 Jul – 4 Aug $77,300
100% · Brad Kelly
J-26-0201 Offsite
AFC maingate gearbox — exchange overhaul
Ulan West Operations · 14 Jul – 15 Aug $77,300
100% · Brad Kelly
J-26-0192 Onsite
Pump station onsite rebuild — 3 × pumps
Tahmoor Mine · 1 Aug – 9 Aug $39,561
100% · Josh Tranter
Drop here