Ulan West Operations — Exchange leg overhaul — 24 × 400 mm legs (W6 rotation pool)
Demo 06 Oct 2026
← Jobs Quote Q-26-0415
$154,800value (ex GST)
$50,235cost to date · 50% done
$100,470forecast cost · budget $98,500
35.1%forecast margin · quoted 36.4%
$0invoiced
Coststimesheets, parts issued, subcontract & freight
DateCategoryDescriptionRefAmount
01 Oct 2026 Workshop labour & parts Workshop labour & parts issued — w/e 01 Oct TS-4884 $13,347.00
26 Sep 2026 Freight Freight — Mudgee ↔ site AP-20805 $1,887.00
26 Sep 2026 Workshop labour & parts Workshop labour & parts issued — w/e 26 Sept TS-4808 $16,738.00
20 Sep 2026 Workshop labour & parts Workshop labour & parts issued — w/e 20 Sept TS-4253 $18,263.00
Offsite overhaulIn progress
Customer
Ulan West Operations
Location
Mudgee workshop
Dates
15 Sep 2026 – 20 Oct 2026
Supervisor
Brad Kelly
Crew
3
Order no.
4500574213
Cost by category
Workshop labour & parts$48,348
Freight$1,887