Narrabri Underground — LW 110 → LW 111 longwall relocation — take-off & install
Demo 06 Oct 2026
← Jobs Quote Q-26-0413
$1,222,206value (ex GST)
$401,803cost to date · 45% done
$892,896forecast cost · budget $797,228
26.9%forecast margin · quoted 34.8%
$488,882invoiced
Coststimesheets, parts issued, subcontract & freight
DateCategoryDescriptionRefAmount
02 Oct 2026 Freight Freight — Mudgee ↔ site AP-20247 $3,730.00
02 Oct 2026 Travel & accommodation Accommodation & meals AP-20117 $57,789.00
02 Oct 2026 Subcontract Subcontractor invoice AP-20302 $40,219.00
02 Oct 2026 Labour Timesheets — week ending 02 Oct TS-4418 $300,065.00
Longwall relocationIn progress
Customer
Narrabri Underground
Location
Narrabri UG
Dates
27 Sep 2026 – 18 Oct 2026
Supervisor
Dean Purcell
Crew
24
Order no.
276512
Cost by category
Labour$300,065
Subcontract$40,219
Travel & accommodation$57,789
Freight$3,730