Phoenix

J-26-0201

Ulan West Operations — AFC maingate gearbox — exchange overhaul
Demo 06 Oct 2026
$77,300value (ex GST)
$49,699cost to date · 100% done
$49,699forecast cost · budget $49,700
35.7%forecast margin · quoted 35.7%
$77,300invoiced
Coststimesheets, parts issued, subcontract & freight
DateCategoryDescriptionRefAmount
09 Aug 2026 Workshop labour & parts Workshop labour & parts issued — w/e 09 Aug TS-4124 $9,685.00
02 Aug 2026 Workshop labour & parts Workshop labour & parts issued — w/e 02 Aug TS-4877 $10,941.00
30 Jul 2026 Freight Freight — Mudgee ↔ site AP-20428 $3,700.00
27 Jul 2026 Workshop labour & parts Workshop labour & parts issued — w/e 27 July TS-4121 $14,256.00
20 Jul 2026 Workshop labour & parts Workshop labour & parts issued — w/e 20 July TS-4862 $11,117.00
Offsite overhaulInvoiced
Customer
Ulan West Operations
Location
Mudgee workshop
Dates
14 Jul 2026 – 15 Aug 2026
Supervisor
Brad Kelly
Crew
3
Order no.
4500816677
Cost by category
Workshop labour & parts$45,999
Freight$3,700