Phoenix

J-26-0197

Ulan West Operations — Shield base-lift cylinder modification — design review
Demo 06 Oct 2026
← Jobs Quote Q-26-0427
$12,480value (ex GST)
$7,067cost to date · 100% done
$7,067forecast cost · budget $7,680
43.4%forecast margin · quoted 38.5%
$0invoiced
Workshop items+ Book in
No workshop items on this job.
Invoices
Not invoiced yet.
Coststimesheets, parts issued, subcontract & freight
DateCategoryDescriptionRefAmount
09 Sep 2026 Labour Timesheets — week ending 09 Sept TS-4919 $1,925.00
02 Sep 2026 Labour Timesheets — week ending 02 Sept TS-4805 $1,418.00
26 Aug 2026 Labour Timesheets — week ending 26 Aug TS-4415 $1,644.00
19 Aug 2026 Labour Timesheets — week ending 19 Aug TS-4992 $2,080.00
EngineeringComplete
Customer
Ulan West Operations
Location
Mudgee office
Dates
12 Aug 2026 – 16 Sep 2026
Supervisor
Tom Walsh
Crew
3
Order no.
4500246984
Cost by category
Labour$7,067