$27,200value (ex GST)
$16,578cost to date · 100% done
$16,578forecast cost · budget $17,450
39.1%forecast margin · quoted 35.8%
$0invoiced
Workshop items+ Book in
WS-26-0834 Sprocket assembly × 2Bay 4 — heavy · Mia Fenwick · due 26 Sep 2026
Dispatched Invoices
Not invoiced yet.
Coststimesheets, parts issued, subcontract & freight
| Date | Category | Description | Ref | Amount | |
|---|---|---|---|---|---|
| 22 Sep 2026 | Workshop labour & parts | Workshop labour & parts issued — w/e 22 Sept | TS-4600 | $3,927.00 | |
| 15 Sep 2026 | Workshop labour & parts | Workshop labour & parts issued — w/e 15 Sept | TS-4288 | $4,193.00 | |
| 12 Sep 2026 | Freight | Freight — Mudgee ↔ site | AP-20200 | $1,758.00 | |
| 09 Sep 2026 | Workshop labour & parts | Workshop labour & parts issued — w/e 09 Sept | TS-4336 | $3,099.00 | |
| 02 Sep 2026 | Workshop labour & parts | Workshop labour & parts issued — w/e 02 Sept | TS-4980 | $3,601.00 | |
Offsite overhaulComplete
- Customer
- Mandalong Mine
- Location
- Mudgee workshop
- Dates
- 27 Aug 2026 – 28 Sep 2026
- Supervisor
- Brad Kelly
- Crew
- 3
- Order no.
- 900593
Cost by category
Workshop labour & parts$14,820
Freight$1,758
Phoenix Underground Pty Ltd
69 Depot Road, Mudgee NSW 2850 · (02) 8074 4988 · admin@phoenixug.com.au
ABN 41 618 552 907
Job card
J-26-0189
Start 27 Aug 2026
Finish 28 Sep 2026
Supervisor Brad Kelly
Customer
Mandalong Mine
Mudgee workshop
Order 900593
BSL sprocket assembly rebuild — spare
| Sprocket assembly rebuild — 7-tooth, 42 mm chain | 2 |
| Freight — mine site ↔ Mudgee workshop | 1 |
| WS-26-0834 | Sprocket assembly × 2 | Bay 4 — heavy | Dispatched |
Offsite & onsite overhauls · Longwall relocations · Condition monitoring · Engineering — NSW & QLD