Mandalong Mine — BSL sprocket assembly rebuild — spare
Demo 06 Oct 2026
← Jobs Quote Q-26-0419
$27,200value (ex GST)
$16,578cost to date · 100% done
$16,578forecast cost · budget $17,450
39.1%forecast margin · quoted 35.8%
$0invoiced
Coststimesheets, parts issued, subcontract & freight
DateCategoryDescriptionRefAmount
22 Sep 2026 Workshop labour & parts Workshop labour & parts issued — w/e 22 Sept TS-4600 $3,927.00
15 Sep 2026 Workshop labour & parts Workshop labour & parts issued — w/e 15 Sept TS-4288 $4,193.00
12 Sep 2026 Freight Freight — Mudgee ↔ site AP-20200 $1,758.00
09 Sep 2026 Workshop labour & parts Workshop labour & parts issued — w/e 09 Sept TS-4336 $3,099.00
02 Sep 2026 Workshop labour & parts Workshop labour & parts issued — w/e 02 Sept TS-4980 $3,601.00
Offsite overhaulComplete
Customer
Mandalong Mine
Location
Mudgee workshop
Dates
27 Aug 2026 – 28 Sep 2026
Supervisor
Brad Kelly
Crew
3
Order no.
900593
Cost by category
Workshop labour & parts$14,820
Freight$1,758