Springvale Mine — Shuttle car SC-02 — traction gearbox rebuild
Demo 06 Oct 2026
← Jobs Quote Q-26-0417
$34,000value (ex GST)
$19,597cost to date · 95% done
$20,628forecast cost · budget $21,050
39.3%forecast margin · quoted 38.1%
$0invoiced
Coststimesheets, parts issued, subcontract & freight
DateCategoryDescriptionRefAmount
28 Sep 2026 Workshop labour & parts Workshop labour & parts issued — w/e 28 Sept TS-4256 $6,253.00
22 Sep 2026 Freight Freight — Mudgee ↔ site AP-20470 $1,722.00
22 Sep 2026 Workshop labour & parts Workshop labour & parts issued — w/e 22 Sept TS-4537 $5,276.00
16 Sep 2026 Workshop labour & parts Workshop labour & parts issued — w/e 16 Sept TS-4679 $6,346.00
Offsite overhaulQA & handover
Customer
Springvale Mine
Location
Mudgee workshop
Dates
10 Sep 2026 – 04 Oct 2026
Supervisor
Brad Kelly
Crew
3
Order no.
185440
Cost by category
Workshop labour & parts$17,875
Freight$1,722