Phoenix

J-26-0208

Narrabri Underground — Condition monitoring program FY27 — Narrabri Underground
Demo 06 Oct 2026
← Jobs Quote Q-26-0438
$95,600value (ex GST)
$14,339cost to date · 27% done
$53,107forecast cost · budget $55,904
44.4%forecast margin · quoted 41.5%
$23,900invoiced
Coststimesheets, parts issued, subcontract & freight
DateCategoryDescriptionRefAmount
17 Sep 2026 Labour Timesheets — week ending 17 Sept TS-4625 $2,991.00
28 Aug 2026 Labour Timesheets — week ending 28 Aug TS-4108 $2,684.00
19 Aug 2026 Subcontract Subcontractor invoice AP-20640 $2,027.00
09 Aug 2026 Labour Timesheets — week ending 09 Aug TS-4385 $3,818.00
20 Jul 2026 Labour Timesheets — week ending 20 July TS-4558 $2,819.00
Condition monitoringIn progress
Customer
Narrabri Underground
Location
Site + Mudgee office
Dates
01 Jul 2026 – 01 Jul 2027
Supervisor
Sophie Lindqvist
Crew
2
Order no.
131783
Cost by category
Labour$12,312
Subcontract$2,027