Phoenix

J-26-0206

Ulan West Operations — Condition monitoring program FY27 — Ulan West Operations
Demo 06 Oct 2026
← Jobs Quote Q-26-0436
$257,600value (ex GST)
$38,347cost to date · 27% done
$142,026forecast cost · budget $149,504
44.9%forecast margin · quoted 42.0%
$64,400invoiced
Coststimesheets, parts issued, subcontract & freight
DateCategoryDescriptionRefAmount
17 Sep 2026 Labour Timesheets — week ending 17 Sept TS-4606 $8,205.00
28 Aug 2026 Labour Timesheets — week ending 28 Aug TS-4661 $8,811.00
19 Aug 2026 Subcontract Subcontractor invoice AP-20690 $2,027.00
09 Aug 2026 Labour Timesheets — week ending 09 Aug TS-4223 $10,483.00
20 Jul 2026 Labour Timesheets — week ending 20 July TS-4113 $8,821.00
Condition monitoringIn progress
Customer
Ulan West Operations
Location
Site + Mudgee office
Dates
01 Jul 2026 – 01 Jul 2027
Supervisor
Sophie Lindqvist
Crew
2
Order no.
4500979100
Cost by category
Labour$36,320
Subcontract$2,027