$1,106,120value (ex GST)
$759,242cost to date · 100% done
$759,242forecast cost · budget $723,088
31.4%forecast margin · quoted 34.6%
$1,106,120invoiced
Workshop items+ Book in
No workshop items on this job.
Coststimesheets, parts issued, subcontract & freight
| Date | Category | Description | Ref | Amount | |
|---|---|---|---|---|---|
| 29 May 2026 | Labour | Timesheets — week ending 29 May | TS-4663 | $164,247.00 | |
| 24 May 2026 | Labour | Timesheets — week ending 24 May | TS-4294 | $129,329.00 | |
| 22 May 2026 | Freight | Freight — Mudgee ↔ site | AP-20205 | $7,770.00 | |
| 22 May 2026 | Travel & accommodation | Accommodation & meals | AP-20378 | $106,722.00 | |
| 22 May 2026 | Subcontract | Subcontractor invoice | AP-20134 | $87,780.00 | |
| 19 May 2026 | Labour | Timesheets — week ending 19 May | TS-4894 | $123,905.00 | |
| 14 May 2026 | Labour | Timesheets — week ending 14 May | TS-4547 | $139,489.00 | |
Longwall relocationInvoiced
- Customer
- Mandalong Mine
- Location
- Mandalong
- Dates
- 09 May 2026 – 03 Jun 2026
- Supervisor
- Dean Purcell
- Crew
- 24
- Order no.
- 445947
Cost by category
Labour$556,970
Subcontract$87,780
Travel & accommodation$106,722
Freight$7,770
Phoenix Underground Pty Ltd
69 Depot Road, Mudgee NSW 2850 · (02) 8074 4988 · admin@phoenixug.com.au
ABN 41 618 552 907
Job card
J-26-0202
Start 09 May 2026
Finish 03 Jun 2026
Supervisor Dean Purcell
Customer
Mandalong Mine
Mandalong
Order 445947
LW 24 → LW 25 longwall relocation
| Mechanical fitter (UG, coal-ticketed) | 4752 |
| Site supervisor | 528 |
| Electrician (UG) | 528 |
| Mechanical engineer | 60 |
| Equipment hire — transporters & cranage | 22 |
| Travel, accommodation & meals | 484 |
| Freight — mine site ↔ Mudgee workshop | 4 |
Offsite & onsite overhauls · Longwall relocations · Condition monitoring · Engineering — NSW & QLD