Phoenix

J-26-0200

Moolarben Underground — LW 107 mid-panel shield service — 136 shields
Demo 06 Oct 2026
← Jobs Quote Q-26-0430
$337,993value (ex GST)
$224,267cost to date · 97% done
$231,203forecast cost · budget $218,116
31.6%forecast margin · quoted 35.5%
$0invoiced
Workshop items+ Book in
No workshop items on this job.
Invoices
Not invoiced yet.
Coststimesheets, parts issued, subcontract & freight
DateCategoryDescriptionRefAmount
28 Sep 2026 Labour Timesheets — week ending 28 Sept TS-4978 $85,526.00
26 Sep 2026 Freight Freight — Mudgee ↔ site AP-20743 $3,804.00
26 Sep 2026 Parts & materials Parts issued from Mudgee stores AP-20875 $45,159.00
23 Sep 2026 Labour Timesheets — week ending 23 Sept TS-4640 $89,778.00
Onsite overhaulQA & handover
Customer
Moolarben Underground
Location
Moolarben — LW 107 face
Dates
18 Sep 2026 – 03 Oct 2026
Supervisor
Mick Sullivan
Crew
10
Order no.
PO627868
Cost by category
Labour$175,304
Parts & materials$45,159
Freight$3,804