$337,993value (ex GST)
$224,267cost to date · 97% done
$231,203forecast cost · budget $218,116
31.6%forecast margin · quoted 35.5%
$0invoiced
Workshop items+ Book in
No workshop items on this job.
Invoices
Not invoiced yet.
Coststimesheets, parts issued, subcontract & freight
| Date | Category | Description | Ref | Amount | |
|---|---|---|---|---|---|
| 28 Sep 2026 | Labour | Timesheets — week ending 28 Sept | TS-4978 | $85,526.00 | |
| 26 Sep 2026 | Freight | Freight — Mudgee ↔ site | AP-20743 | $3,804.00 | |
| 26 Sep 2026 | Parts & materials | Parts issued from Mudgee stores | AP-20875 | $45,159.00 | |
| 23 Sep 2026 | Labour | Timesheets — week ending 23 Sept | TS-4640 | $89,778.00 | |
Onsite overhaulQA & handover
- Customer
- Moolarben Underground
- Location
- Moolarben — LW 107 face
- Dates
- 18 Sep 2026 – 03 Oct 2026
- Supervisor
- Mick Sullivan
- Crew
- 10
- Order no.
- PO627868
Cost by category
Labour$175,304
Parts & materials$45,159
Freight$3,804
Phoenix Underground Pty Ltd
69 Depot Road, Mudgee NSW 2850 · (02) 8074 4988 · admin@phoenixug.com.au
ABN 41 618 552 907
Job card
J-26-0200
Start 18 Sep 2026
Finish 03 Oct 2026
Supervisor Mick Sullivan
Customer
Moolarben Underground
Moolarben — LW 107 face
Order PO627868
LW 107 mid-panel shield service — 136 shields
| Mechanical fitter (UG, coal-ticketed) | 1440 |
| Site supervisor | 288 |
| Electrician (UG) | 144 |
| Leg seal kit — 320 mm bore | 41 |
| DA ram seal kit — 160 mm | 34 |
| Side shield ram seal kit — 100 mm | 27 |
| Hydraulic hose DN25 4-wire, made up (per m) | 82 |
| Staple-lock fitting DN25 | 136 |
| FRAS-rated roof support foam — cut to site spec | 27 |
| Freight — mine site ↔ Mudgee workshop | 2 |
Offsite & onsite overhauls · Longwall relocations · Condition monitoring · Engineering — NSW & QLD