J-26-0182

Moolarben Underground — LW 106 → LW 107 longwall relocation
Demo 06 Oct 2026
$983,028value (ex GST)
$607,150cost to date · 100% done
$607,150forecast cost · budget $625,928
38.2%forecast margin · quoted 36.3%
$983,028invoiced
Coststimesheets, parts issued, subcontract & freight
DateCategoryDescriptionRefAmount
18 Jun 2026 Labour Timesheets — week ending 18 June TS-4555 $147,330.00
12 Jun 2026 Freight Freight — Mudgee ↔ site AP-20694 $7,178.00
12 Jun 2026 Subcontract Subcontractor invoice AP-20331 $88,464.00
12 Jun 2026 Labour Timesheets — week ending 12 June TS-4433 $195,717.00
06 Jun 2026 Labour Timesheets — week ending 06 June TS-4274 $168,461.00
Longwall relocationInvoiced
Customer
Moolarben Underground
Location
Moolarben UG
Dates
31 May 2026 – 24 Jun 2026
Supervisor
Mick Sullivan
Crew
24
Order no.
PO872541
Cost by category
Labour$511,508
Subcontract$88,464
Freight$7,178