J-26-0195

Grosvenor Mine — Leg cylinder overhaul — 12 × 320 mm
Demo 06 Oct 2026
← Jobs Quote Q-26-0425
$68,160value (ex GST)
$39,852cost to date · 92% done
$43,317forecast cost · budget $42,890
36.4%forecast margin · quoted 37.1%
$0invoiced
Coststimesheets, parts issued, subcontract & freight
DateCategoryDescriptionRefAmount
28 Sep 2026 Workshop labour & parts Workshop labour & parts issued — w/e 28 Sept TS-4199 $10,232.00
21 Sep 2026 Workshop labour & parts Workshop labour & parts issued — w/e 21 Sept TS-4906 $10,898.00
18 Sep 2026 Freight Freight — Mudgee ↔ site AP-20121 $1,719.00
15 Sep 2026 Workshop labour & parts Workshop labour & parts issued — w/e 15 Sept TS-4956 $8,077.00
08 Sep 2026 Workshop labour & parts Workshop labour & parts issued — w/e 08 Sept TS-4259 $8,926.00
Offsite overhaulQA & handover
Customer
Grosvenor Mine
Location
Mudgee workshop
Dates
01 Sep 2026 – 05 Oct 2026
Supervisor
Brad Kelly
Crew
3
Order no.
983417
Cost by category
Workshop labour & parts$38,133