J-26-0193

Moranbah North Mine — AFC tailgate gearbox overhaul
Demo 06 Oct 2026
$77,300value (ex GST)
$49,203cost to date · 100% done
$49,203forecast cost · budget $49,700
36.3%forecast margin · quoted 35.7%
$77,300invoiced
Coststimesheets, parts issued, subcontract & freight
DateCategoryDescriptionRefAmount
28 Jul 2026 Workshop labour & parts Workshop labour & parts issued — w/e 28 July TS-4211 $13,574.00
22 Jul 2026 Workshop labour & parts Workshop labour & parts issued — w/e 22 July TS-4848 $9,767.00
19 Jul 2026 Freight Freight — Mudgee ↔ site AP-20700 $3,663.00
15 Jul 2026 Workshop labour & parts Workshop labour & parts issued — w/e 15 July TS-4380 $11,771.00
09 Jul 2026 Workshop labour & parts Workshop labour & parts issued — w/e 09 July TS-4749 $10,428.00
Offsite overhaulInvoiced
Customer
Moranbah North Mine
Location
Mudgee workshop
Dates
02 Jul 2026 – 04 Aug 2026
Supervisor
Brad Kelly
Crew
3
Order no.
336173
Cost by category
Workshop labour & parts$45,540
Freight$3,663