$40,200value (ex GST)
$0cost to date · 0% done
$24,350forecast cost · budget $24,350
39.4%forecast margin · quoted 39.4%
$0invoiced
Workshop items+ Book in
No workshop items on this job.
Invoices
Not invoiced yet.
Coststimesheets, parts issued, subcontract & freight
| Date | Category | Description | Ref | Amount |
|---|
Nothing here yet — use “Add cost” to create the first one.
Offsite overhaulPlanned
- Customer
- Appin Mine
- Location
- Mudgee workshop
- Dates
- 12 Oct 2026 – 05 Nov 2026
- Supervisor
- Brad Kelly
- Crew
- 3
- Order no.
- 602005
Cost by category
No costs yet.
Phoenix Underground Pty Ltd
69 Depot Road, Mudgee NSW 2850 · (02) 8074 4988 · admin@phoenixug.com.au
ABN 41 618 552 907
Job card
J-26-0191
Start 12 Oct 2026
Finish 05 Nov 2026
Supervisor Brad Kelly
Customer
Appin Mine
Mudgee workshop
Order 602005
Advance ram overhaul — 18 × 140 mm
| Advance ram overhaul — 140 mm | 18 |
| Freight — mine site ↔ Mudgee workshop | 1 |